Sunday, February 10, 2013

External Cladding works continue

Well with  plasterer finishing so quickly the pressure is on for us to complete the external cladding. So this weekend we tackle the Back wall. It has been dam hot and when you are getting the reflection of the insulation it makes it even worse. But another weekend down anf the back wall is finished ( only 5 to go)



Saturday, February 9, 2013

Just a blink an the internal walls are done

We arrive back after a fortnight away and the internal lining is done. Blink of an eye there are no more container walls an d now just gyprock. It looks great however somewhat sad .






Thursday, January 31, 2013

More tradies arrive and Plumbing works commence

Yes just like the internal lining another tradie is at work this time doing the first fix, sewer water and gas.  It is knocked over in 2 days and looks great.
   


Friday, January 25, 2013

Internal wall linings go up

So now that we have started cladding the outside we are also doing the inside. This is one of those jobs we have been looking forward to, because we are not doing it J. After weeks of fitting batons the Plasterer is in and has made a start. Those Container walls are disappearing fast !





Thursday, December 27, 2012

All hands on Deck as we go cladding crazy


Well this is where we go Cladding crazy it is the days leading up to Christmas and the kids are here so we have a crew of 4. The plumber is up doing first fix, Water, sewer and as but that is next week’s story.

So our goal is to complete down one side and this one is probably the toughest as it has 3 windows and three container joins. First job is to weld a number of mounting brackets to allow the first row of cladding to be secured, below the skin and of course must be level once this is done and we fit the first row it is easy street. Kirsten is in charge of screws and clips and tools while Tina and Jason are in charge of cladding supply bringing around full lengths as well as cut lengths. It all goes well and progresses fast until we get to the windows. This slows us down and it is hot dam hot. We make good progress on the first day but stop in time for a swim at Alligators nest in the rain.


 Second day back into it and finishing off all the cuts around the window and al l the way to the second to last row. Once again it is hot and sticky as it has rained. We cannot do the last row until we get a special piece of flashing made to finish it off to the container roof. So if water ever does get under there or the roof gets ripped off in a cyclone it si still sealed off to the wall.
 

Sunday, December 16, 2012

External Cladding Pilot wall


OK here we go this is absolutely the last weekend we are putting up batons all the rooms are done. So on we go to the External cladding. Yes this is where we say goodbye to Shipping containers and although it will take a while one wall is gone. This is our pilot wall and it all went pretty well with only one job required. It looks really good but we are not sure about the trial colour


Saturday, December 15, 2012

External door 2.


Well back again next weekend same task but at least I did a door last weekend so this one should be easier just the same but a mirror image. Got this one in easy as well and Tina finished all the insulation works







Thursday, December 6, 2012

External doors


Well we have now moved on to the last 2 structural items left to fit 2 external doors in the laundry and main bedroom. Due to cricket and work commitments as I’m currently working in Townsville we have had limited time the last few weekends but have managed to get a door in the laundry as well as some more wall batons and Tina has started on the ceiling insulation.



Sunday, November 11, 2012

Just a couple of batons needed !!!!


Well we finally put the 2 exhaust outlets for the range hood and bathroom exhaust fan in, they have been on the to do list for ever. We have commenced the internal door frames with 3 of the 5 completed.


 
Now the next job was to put up some timber batons in the corners as the metal is too thick to screw into for fitting the gyprock , The ends of the containers are also made out of really thick steel so we decided to baton this off as well. But shipping containers are not that straight so we have also done this where the walls are not straight. Hm as you will see in photos coming soon that tis nearly al the walls so this job just goes on and on each weekend with no end in sight.
 

Saturday, October 27, 2012

Septic tank installed


We now have septic tank, sewer to the house as well as evaporation trenches. This was a job for a plumber and it looks good and increased our embankment site next to the rain water tank

 



Saturday, October 20, 2012

House pad site works completed

We have finished running all the underground services now with water power and most recently sewerage run over to the house. This has allowed us to finish putting down road base up at the site house pad and we have added road base under the house and deck which will reduce the impact of wet season red mud. It was pretty hard work raking out all the road base under the house but all looks good now.








 

 

Saturday, October 13, 2012

The workshop gets a gutter and downpipe upgrade


When  we first roofed the workshop we were supplied the wrong gutter but we installed it anyway under the guidance of the great fishing guru !! Only to receive the correct gutter at a later date which was still like 9 months ago. As we have been focusing on the house it has been neglected.  So I’m not entirely sure of the circumstances but recently we installed the new correct one piece gutter and down pipe to the tank which includes a leaf extractor and first flush system. We also incorporated the same system that we used up the house which was to install a down pipe at the other end of the gutter which will allow run off in tomes of heavy rain . ( that is a little funny really it is Tully)