Saturday, October 27, 2012

Septic tank installed


We now have septic tank, sewer to the house as well as evaporation trenches. This was a job for a plumber and it looks good and increased our embankment site next to the rain water tank

 



Saturday, October 20, 2012

House pad site works completed

We have finished running all the underground services now with water power and most recently sewerage run over to the house. This has allowed us to finish putting down road base up at the site house pad and we have added road base under the house and deck which will reduce the impact of wet season red mud. It was pretty hard work raking out all the road base under the house but all looks good now.








 

 

Saturday, October 13, 2012

The workshop gets a gutter and downpipe upgrade


When  we first roofed the workshop we were supplied the wrong gutter but we installed it anyway under the guidance of the great fishing guru !! Only to receive the correct gutter at a later date which was still like 9 months ago. As we have been focusing on the house it has been neglected.  So I’m not entirely sure of the circumstances but recently we installed the new correct one piece gutter and down pipe to the tank which includes a leaf extractor and first flush system. We also incorporated the same system that we used up the house which was to install a down pipe at the other end of the gutter which will allow run off in tomes of heavy rain . ( that is a little funny really it is Tully)